It is possible to required shutting down all LPARs, followed by power server for some UPS / Cooling / Network maintenance activity at DC. In such cases to shutdown and start entire SAP related infrastructure refer below steps:
SAP Infra shutdown process
- Put the Linux cluster related to SAP App and DB in maintenance mode
- SAP team should stop application servers
- SAP team should stop database servers
- Stop the pacemaker cluster serives in Application & Database servers as per Pacemaker start and stop for Hana DB and application servers
- Shutdown all the LPAR's using:
- shutdown -h now
- Note: Backup LPAR should be powered of at last
- Shutdown second VIOS server
- Shutdown first VIOS server
- Shutdown second physical host
- Shutdown first physical host
- Shutdown HMC VM
- Shutdown Physical server hosting HMC VM
- Shutdown storage
- Shutdown Tape Library
SAP Infra start up procedure
- Start Tape Library
- Start storage
- Start Dell host
- Start HMC VM
- Note: After storage, wait for 15-20mins for start physical hosts
- Start primary physical host
- Start seconday physical host
- Start primary VIOS server
- Start secondary VIOS server
- Start Database primary LPAR.
- Start Database secondary LPAR.
- SAP team start the Database in both the LPARs, Replication between the databases should work
- Start the pacemaker cluster in primary node as per Pacemaker start and stop for Hana DB and application servers
- Start the pacemaker cluster in secondary node
- Primary and Secondary nodes cluster services are in maintanence mode, because custer services was stopped in the maintenance mode state
- Get confirmation from SAP team on Database & Replication services working status
- Remove the database primary node from the maintenance using:
- crm node ready <nodename>
- Remove the database secondary node from the maintenance
- Get confirmation from SAP team on the Database & Replication services working status
- After nodes are in online state, Then only cluster services is in start state. Check cluster services health using:
- crm status
- Start the Application Primary LPAR
- Start the Application Secondary LPAR
- Primary and Secondary nodes are in maintanence mode, because custer services was stopped in maintenance mode state
- Remove the Application primary node from the maintenance using:
- crm node ready <nodename>
- Remove the Application secondary node from the maintenance.
- After nodes are in online state, Then cluster services is in start state and able to see all the mount points
- SAP team will start APP services in Primary & Secondary nodes as per Pacemaker start and stop for Hana DB and application servers
- Start all the LPARs
- Note: Backup LPAR should start last
Refer: